Santa Maria River Bridge Widening

Description: Near Santa Maria, from north Junction 135 to north Junction 166. Add one northbound and one southbound lane.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Luis Obispo, Santa Barbara
City
Zip Code
 
Senate District
15
Assembly District 33
Congressional District 23, 24
 
Caltrans District
05
 
 
County/State Route San Luis Obispo 101
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  220    203  
Peak Period Time Savings (minutes)  21300    20000  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Lisa Lowerison (805)542-4764   lisa_lowerison@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Lisa Lowerison (805)542-4764   lisa_lowerison@dot.ca.gov
Right of Way Phase
Department of Transportation Lisa Lowerison (805)542-4764   lisa_lowerison@dot.ca.gov
Construction Phase
Department of Transportation Lisa Lowerison (805)542-4764   lisa_lowerison@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$31,600 $-426 $31,174
Non-bond Funding
State/Federal*
$5,382 $-127 $5,255
Local**
$13,870 $-2,442 $11,428
Non Budgeted ETC
$0 $0 $0
 
Total**** $50,852 $-2,995 $47,857

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,796 $0 $1,796 $1,639
Design(PS&E)
$4,112 $0 $4,112 $4,198
Right of Way
$644 $-127 $517 $372
Construction
$44,300 $-2,868 $41,432 $40,347
 
Total* $50,852 $-2,995 $47,857 $46,557

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

12/15/2009 
 

 
 

12/15/2009 
100   

12/15/2009 


Begin Right of Way Phase

End Right of Way Phase
11/04/2008 

10/30/2009 
 

 
11/04/2008 

10/30/2009 
100  10/01/2007 

10/30/2009 
13 

Begin Construction Phase

End Construction Phase
01/15/2011 

04/01/2014 
 

 
01/15/2011 

04/01/2014 
100  07/15/2011 

03/12/2015 
-6 

-11 
Begin Closeout Phase

End Closeout Phase
04/01/2014 

07/15/2015 
 

07/31/2017 
04/01/2014 

07/15/2015 
50  03/12/2015 

04/18/2017 
-11 

-21 
Corridor System Management Plan
Adoption Date 10/01/2011    10/01/2011  05/01/2012  -7 
Implementation Date 10/01/2011    10/01/2011  06/06/2012  -8 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 220 203
Peak Period Time Savings (minutes) 21300 20000

Bond Funding Cost
Adopted:
$31,600,000
Current Approved:
$31,174,000
Actual Expenditures:
$30,095,000

 

Status as of December 31, 2023.