Santa Maria River Bridge Widening |
Description: Near Santa Maria, from north Junction 135 to north Junction 166. Add one northbound and one southbound lane.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Luis Obispo, Santa Barbara |
City | |
Zip Code | |
Senate District |
15 |
Assembly District | 33 |
Congressional District | 23, 24 |
Caltrans District |
05 |
County/State Route | San Luis Obispo 101 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 220 | 203 |
Peak Period Time Savings (minutes) | 21300 | 20000 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Lisa Lowerison | (805)542-4764 | lisa_lowerison@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Lisa Lowerison | (805)542-4764 | lisa_lowerison@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Lisa Lowerison | (805)542-4764 | lisa_lowerison@dot.ca.gov | |
Construction Phase |
Department of Transportation | Lisa Lowerison | (805)542-4764 | lisa_lowerison@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$31,600 | $-426 | $31,174 | ||||
Non-bond Funding | |||||||
State/Federal* |
$5,382 | $-127 | $5,255 | ||||
Local** |
$13,870 | $-2,442 | $11,428 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $50,852 | $-2,995 | $47,857 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$1,796 | $0 | $1,796 | $1,639 | |||
Design(PS&E) |
$4,112 | $0 | $4,112 | $4,198 | |||
Right of Way |
$644 | $-127 | $517 | $372 | |||
Construction |
$44,300 | $-2,868 | $41,432 | $40,347 | |||
Total* | $50,852 | $-2,995 | $47,857 | $46,557 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/15/2009 |
|
12/15/2009 |
100 | 12/15/2009 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
11/04/2008 10/30/2009 |
|
11/04/2008 10/30/2009 |
100 | 10/01/2007 10/30/2009 |
13 0 |
|
Begin Construction Phase
End Construction Phase |
01/15/2011 04/01/2014 |
|
01/15/2011 04/01/2014 |
100 | 07/15/2011 03/12/2015 |
-6 -11 |
|
Begin Closeout Phase
End Closeout Phase |
04/01/2014 07/15/2015 |
07/31/2017 |
04/01/2014 07/15/2015 |
50 | 03/12/2015 04/18/2017 |
-11 -21 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 10/01/2011 | 10/01/2011 | 0 | 05/01/2012 | -7 | ||
Implementation Date | 10/01/2011 | 10/01/2011 | 0 | 06/06/2012 | -8 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 220 | 203 |
Peak Period Time Savings (minutes) | 21300 | 20000 |
Bond Funding Cost | |
---|---|
Adopted: |
$31,600,000 |
Current Approved: |
$31,174,000 |
Actual Expenditures: |
$30,095,000 |
Status as of December 31, 2023.